Access the project information dialog box using Project | Project Information from the main menu.

computer science

Description

Application Development Project

 

Estimated cost - $100,000

Estimated duration – 20 weeks (US Holiday Calendar , 40 hrs weeks )

 

Staff required:

 

  • Project Manager – Bill - $100/hour
  • Technical Manager  – Sue - $100/hour
  • Developer  – Drake - $50/hour
  • Business Analyst – John - $25/hour

 

Materials Required

Laptops – 4 @ $1000/- each

 

Project Processes:

  • Initiating
    • Project Charter/Kick Off Meeting      Hours: 2                      Staff: Bill
  • Planning (summary task)
    • WBS (week one)
      • Duration: 5 days         Hours: 8 each/day       Staff: John, Drake
  • Executing (summary task)
    • Design (week 2 ,3 and 4)
      • Duration: 15 days       Hours: 8 each /day      Staff: Sue, John, Drake
  • Design Document created - Milestone
    • Build App (Week 5 to 12)
      • Duration: 40 days       Hours: 8 each /day      Staff: Sue/Drake
  • App ready for testing - Milestone
    • Test App
      • Duration: Week 11 - 13          Hours: 8 each/day       Staff: John/Drake
    • Changes/Fixes after testing
      • Duration: Week 14 to 17        Hours: 8 each /day      Staff: Sue/Drake
  • App ready for testing V2 – Milestone
    • Test App
      • Duration: Week 18 - 19          Hours: 8 each/day       Staff: John/Drake
  • App ready for Go Live - Milestone

 

  • Monitor and Control
  • Closing

Exercise 1 – Create a project

 

  1. Create a project file
    1. Open Microsoft Project Professional 2019
    2. Save the new project file using the File | Save option on the main menu.
      Use the file name: “363” YOURNAME

  2. Enter project information
    1. Access the project information dialog box using Project | Project Information from the main menu.
    2. Set the start date to: Monday – Sep 16th, 2019
    3. Leave all other options as the defaults settings.
    4. Close the project information dialog box by selecting OK.

Exercise 2 – Entering tasks

 

  1. Open the project file using File | Open “363” YOURNAME.mpp

 

  1. Insert Tasks below

 

Project Processes:

  • Initiating
    • Project Charter/Kick Off Meeting      Hours: 2                      Staff: Bill
  • Planning (summary task)
    • WBS (week one)
      • Duration: 5 days         Hours: 8 each/day       Staff: John, Drake
  • Executing (summary task)
    • Design (week 2 ,3 and 4)
      • Duration: 15 days       Hours: 8 each /day      Staff: Sue, John, Drake
  • Design Document created - Milestone
    • Build App (Week 5 to 12)
      • Duration: 40 days       Hours: 8 each /day      Staff: Sue/Drake
  • App ready for testing - Milestone
    • Test App
      • Duration: Week 11 - 13          Hours: 8 each/day       Staff: John/Drake
    • Changes/Fixes after testing
      • Duration: Week 14 to 17        Hours: 8 each /day      Staff: Sue/Drake
  • App ready for testing V2 – Milestone
    • Test App
      • Duration: Week 18 - 19          Hours: 8 each/day       Staff: John/Drake
  • App ready for Go Live - Milestone

 

  • Monitor and Control
  • Closing