Questions 1 - Construct the appropriate network diagram
2 - Indicate the critical path.
3 - What is the expected completion time for the project? You can accomplish any one of the following at an additional cost of $1,500: (1)Reduce job 5 by two days.
(2) Reduce job 3 by two days.
(3) Reduce job 7 by two days.
4 - If you save $1,000 for each day that the earliest completion time is
reduced, which action, if any, would you choose?
5 - What is the possibility that the project will take more than 30 days to
complete?
Get Free Quote!
320 Experts Online