MGT 2225
Project
Management for Start-Ups
Final
Examination
Question |
Marks Available |
Your Score |
1 - Schedule Plan |
5 |
|
2 - Purchase and Procurement, Quality Management,
Budget Plan |
5 |
|
3 - Risk Analysis |
6 |
|
4 - Status Report |
4 |
|
5 - Network Diagram |
5 |
|
Bonus |
1 |
|
Total |
25+1 |
|
Question 1 (5 marks)
With details from the
project found in the Case Study, create an Activity-Based Schedule. Utilize a
start date of February 2020 and assume that activities “documentation” and “flow
charts” can be completed in parallel with other tasks.
Question 2 (2*
2.5 marks OR 1*5 marks) Answer
both (a and b) OR c
a.
From the details shared
in the case study, it is clear that a part of the work in improvement of MCCS
Policy is being outsourced. Describe the process involved in this purchasing
and procurement process. (Hint: speak in-terms of SOW and RFP)
b.
Describe the importance of a Quality
Management Plan for the Crosby Manufacturing Corporation in-terms of the MCCS
improvement project.
OR
c. With details found in
the case study, create a budget for this project over 18 months. Assume a total
cost of $500,000.00. Assume also that the bid-process, testing and
documentation will be handled in-house, at no cost to the project, and that
hardware and software costs are paid to the vendor with a 25% deposit, 25% due the month of completion,
and the remainder paid monthly during the duration of the work
Question 3 (6
marks)
This question pertains
to risk analysis of the project. Create a Risk List of any 3 risks based on the
details shared in the case-study (use template). For the risks identified,
create a Risk Response Plan (use template).
Question 4 (4
marks)
Assume that it is Week 8
of the Execution Phase of your group project. At the end of Week 7, you find
yourself ahead of schedule by a week. You have spent $37,500 of your project
funds where you had expected to spend $34,000. You have a team member who has
been ill for the past 4 days and you are unsure when they will return to work,
however their work is not set to begin until Week 11. Additionally, a key
vendor is rumoured to be facing financial difficulties, although they assure
you that it is business as usual. One of your stakeholders has brought this
financial concern to your attention.
Create a basic status
report for Week 8.
Question 5 (2*2.5
marks OR 1*5 marks)
Answer both (a and b) OR c
a.
Using an everyday
example, demonstrate a finish-to-start, start-to-start and finish-to-finish
dependency.
b.
What was the largest
challenge faced by your team when you were executing your Major Group Project?
OR
c.
Create a Network Diagram
for the activities described below. Identify the Critical Path and calculate
the Project Duration.
Activity |
Duration (Days) |
Dependency |
Start |
0 |
- |
A |
5 |
Start |
B |
2 |
Start |
C |
3 |
A,
B |
D |
5 |
Start |
E |
6 |
Start |
F |
4 |
D,
E |